Roadwork is scheduled to begin on the following streets. All work is weather pending and dates may need to be moved forward as needed. Work hours will be approximately 7am-5pm.
6/24 - Ray St. Reclaim work 6/25-6/27 - Eastview Rd. Reclaim work 6/28-7/1 - Wildlife Dr. Reclaim work 7/2 - Partridge Rd. Reclaim work 7/8 - Pheasant Hill Rd. Reclaim work
6/28 - Ray St. Paving binder course. 6/28 & 7/1 - Eastview Rd. Paving binder course. 7/2 - Wildlife Dr. Paving binder course. 7/8 - Partridge Rd. Paving binder course. 7/10 - Pheasant Hill Rd. Paving binder course.
One lane of traffic will be open at all times. Please expect delays and seek alternate routes when possible.