Construction Advisory No. 26 March 24, 2022

MassDOT Project Number: 606043
Construction Advisory No. 26 March 24, 2022
Two Week Look Ahead
Please be advised that this schedule may change due to weather conditions and existing conditions
found while performing the tasks below. This work may impact traffic and require lane and sidewalk closures
limiting access to driveways and entrances to businesses.
The anticipated work over the next two weeks is to install mainline underground utility conduit within the road
between the Fire Station, 72 Main and the 135/85 intersection.
When this work is completed, the contractor will begin the installation of conduit for underground services
between the Fire Station, 72 Main and the 135/85 intersection. This work will include work on private property to
install conduits from the street to the foundation of the building. No work on the foundation itself or inside any
building will be done at this time.
What to Expect for the Week of March 28, 2022 to April 1, 2022
• Continue Utility work along Main Street in front of the Fire Station and CVS
• Delivery of Electric Materials
What to Expect for the Week of April 4, 2022 to April 8, 2022
• Continue Utility work along Main Street in front of the Fire Station and CVS
• Delivery of Electric materials

Additional information about the Main Street Corridor project is available on the
Town’s project website at https://hopkintonmainstreet.com
The Town of Hopkinton appreciates your patience and consideration while we work to
support MassDOT’s project to revitalize our downtown infrastructure.