Construction Advisory No. 41 September 2, 2022

Please be advised that this schedule may change due to weather and existing conditions found while
performing the tasks below. This work may impact traffic and require lane and sidewalk closures limiting
access to driveways and entrances to businesses.

What to Expect for the Week of September 5, 2022, to September 9, 2022

No Work on Monday, September 5th – Labor Day Holiday
• Continue the service connections project wide
East Side of Project
• Continue Comcast Ductbank work on East Main Street
West Side of Project
• Install new granite curb along Main Street working eastbound from West Main Street to the Fire Station
• Continue to Grade and Compact sidewalks between Wood Street and the Fire Station
• Continue forming Concrete Sidewalks from Wood Street towards the Fire Station
• Concrete sidewalk walk will also take place at the end of driveways; affected property owners will be
notified in advance as driveway access will be impacted; Emergency vehicles access will be maintained
• Pleasant Street and Elm Street detours will be utilized as needed

For the most up to date information about the Main Street Corridor project please
visit theTown’s project website at https://hopkintonmainstreet.com
The Town of Hopkinton appreciates your patience and consideration while
we work tosupport MassDOT’s project to revitalize our downtown infrastructure.