TWO WEEK LOOK AHEAD
Please be advised that this schedule may change due to weather conditions and existing
conditions found while performing the tasks below.
What to Expect for the Week of May 10, 2021
• Drainage Installation along Main Street, from the 85/135 intersection to East Main Street continues
• Drainage Installation along Main Street, from the 85/135 intersection to West Main Street continues
• Delivery of Drainage Materials
• MassDOT Survey Crews to continue to locate limits of easements within the corridor from Ash Street to Wood Street
• Verizon to continue installation of new utility poles along the corridor.
This work may impact traffic and require lane and sidewalk closures limiting access to driveways and entrances to
businesses.
What to Expect for the Week of May 17, 2021
• Drainage Installation along Main Street, from the 85/135 intersection to East Main Street continues
• Drainage Installation along Main Street, from the 85/135 intersection to West Main Street continues
• Delivery of Drainage Materials
• MassDOT Survey Crews to continue to locate limits of easements within the corridor from Ash Street to Wood Street
• Verizon to continue installation of new utility poles along the corridor.
This work may impact traffic and require lane and sidewalk closures limiting access to driveways and entrances to
businesses.
Additional information about the Main Street Corridor project is available on the
Town’s project website at https://hopkintonmainstreet.com
The Town of Hopkinton appreciates your patience and consideration while we work to
support MassDOT’s project to revitalize our downtown infrastructure.