Roadwork has been rescheduled for the following streets. All work is weather pending and dates may need to be moved forward as needed. Work hours will be approximately 7am-5pm. Chestnut St work hours will be 9am-3pm.
8/3 – Eastview Rd & Ray St. Adjust driveway aprons. 8/5-8/9 – Wildlife Dr, Pheasant Hill Rd & Partridge Rd. Adjust driveway aprons & sidewalk ramps.. 8/12&13 – Chestnut St. Milling.. 8/14 – Chestnut St. Adjust structures. 8/15&16 – Chestnut St. Paving.
One lane of traffic will be open. Please expect delays and seek alternate routes when possible.