Roadwork is scheduled to begin on the following streets. All work is weather pending and dates may need to be moved forward as needed. Work hours will be approximately 7am-5pm.
6/24 – Ray St. Reclaim work 6/25-6/27 – Eastview Rd. Reclaim work 6/28-7/1 – Wildlife Dr. Reclaim work 7/2 – Partridge Rd. Reclaim work 7/8 – Pheasant Hill Rd. Reclaim work
6/28 – Ray St. Paving binder course. 6/28 & 7/1 – Eastview Rd. Paving binder course. 7/2 – Wildlife Dr. Paving binder course. 7/8 – Partridge Rd. Paving binder course. 7/10 – Pheasant Hill Rd. Paving binder course.
One lane of traffic will be open at all times. Please expect delays and seek alternate routes when possible.